A collaboration between the U.S. Department of Transportation and Lincoln Parks and Recreation, this project is identified as Fletcher Landmark Trail. This proposed project consists of creating a new trail segment to connect to an existing trail network in the City of Lincoln, Lancaster County, Nebraska. View Lincoln Parks and Rec information sheet for details.
Identified as Fletcher Landmark Trail, Lincoln, this proposed project consists of creating a new trail segment to connect
to an existing trail network in the City of Lincoln, Lancaster County, Nebraska. A new 10-foot wide by 5-inch thick concrete
trail, approximately 6,257 feet long, would begin on the southeast corner of the intersection of North 14th Street and Fletcher
Avenue and run along the south side of Fletcher Avenue terminating at the southwest corner of Fletcher Avenue and North 27th
Street. The trail would provide a connection with the existing 14th Street Trail at the southwest corner of North 14th Street and
Fletcher Avenue. The bike trail would cross four named streets: Rockford Drive, Tombstone Ridge Drive, Marmot Point Drive,
and Telluride Drive. The bike trail would also cross one private commercial access drive approximately 600 feet west of the
Fletcher Avenue and North 27th Street intersection.
The purpose of this project is to construct a new off-street multi-use pedestrian/bike trail to extend the existing trail network
and improve pedestrian safety. The project is needed as existing pedestrian and bicycle infrastructure along Fletcher Avenue
between North 14th Street and 27th Street is incomplete.
The planned project would consist of constructing a new 10-foot wide by 5-inch thick concrete trail, reconstructing existing
storm sewer pipes and inlets as needed, and relocating several street light poles. Existing utilities would be reconstructed or
relocated as needed. The project would also include curb ramps that meet Americans with Disabilities Act (ADA) standards at
the intersection of roadways. The trail would connect back to existing sidewalks adjacent to the project as well.
The proposed projects would require the acquisition of additional property rights, which could include new right-of-way (ROW),
control of access (CA), permanent easements (PE), and/or temporary easements (TE). If your property is impacted by this
project, you will be contacted by a representative once the design footprint has been established. Access to adjacent properties
would be maintained during construction but may be limited at times due to phasing requirements.
The project would have minor impact to nearby wetlands. Impacts to wetlands would be permitted through the appropriate
state and federal agency, and would be mitigated as necessary. No impacts are anticipated to the existing North 14th Street
Trail, protected species, or cultural resources.
Construction could begin as early as fall 2023 Spring 2024 with completion anticipated by spring Fall 2024.
A vehicular detour would not be required for this project, but the eastbound right turn lane of Fletcher Avenue approaching
North 27th Street would be closed during construction of the trail adjacent to the turn lane. A pedestrian detour would be
required during construction. The detour would reroute pedestrians at the southwest corner of the North 27th Street and
Fletcher Avenue intersection to the existing sidewalk on the north side of Fletcher Avenue, west to the intersection of Telluride
Drive and Fletcher Avenue, and then south across Fletcher Avenue.
The estimated cost of the proposed project is $1 million. Funding be derived from federal and local funding sources.
City of Lincoln Project:
TAP-55(186) Fletcher Landmark Trail, Lincoln; CN 13442
Dear Owner/Resident,
You are receiving this letter because you own or lease property within the Fletcher Landmark Trail project area. In 2023, the City of Lincoln obtained easements, both temporary and permanent, on 28 properties within the project area. This letter is to serve as a notification that the tree removals for the project are scheduled to begin as early as March 18th 2024 with construction beginning shortly thereafter and those easements wil be needed in order to allow for construction.
If you received compensation intended to cover the expense of moving/removing fences, sprinklers, landscaping, or other private improvements, you should consider completing those removals or relocations at this time. If your property is leased, we would appreciate your assistance in relaying information about the project start to any tenants that reside on the property.
The Fletcher Landmark Trail is anticipated to be complete by the fall of 2024 and additional information on the project can be found on the City of Lincoln's website under the 'Trail Projects' section at https://lincoln.ne.gov/trails.
We appreciate your coordination in this matter.
Sincerely,
Allison Speicher
Allison Speicher, P.E.
Trails and Natural Resources Coordinator
Lincoln Parks & Recreation